Get an occupancy permit from the Mapandan MEO. RA 11032 processing times: 3–20 working days.

Description

An occupancy permit certifies that a building or structure has been completed and inspected in accordance with the approved plans and the National Building Code. It is required before any building may be legally occupied or used.

Requirements

  • Xerox copy of approved building permit
  • Fire safety inspection certificate (from BFP)

Procedure

  1. Request a final inspection from the Municipal Engineering Office.
  2. Submit the as-built plans and inspection report.
  3. Obtain a fire safety inspection certificate from the BFP.
  4. Submit all documents to the MEO for review.
  5. Receive the occupancy permit upon approval.

Service Details

Responsible Office: Municipal Engineering Office (MEO)

Classification: Simple

Mode: in-person

Processing Time: 3 working days (Simple) / 7 working days (Complex) / 20 working days (Highly Technical) per RA 11032

Fee: As scheduled by the MEO

Where to Apply: Municipal Engineering Office, Main Municipal Building, Poblacion

Contact: (075) 696-0831 / 0998-577-3164

Source: Mapandan Citizen’s Charter

Last Updated: August 2025

Report incorrect information

Scanned Document

Scanned page from the official Mapandan Citizen's Charter listing the requirements, fees, processing time, and responsible staff for the service.

Citizens Charter for Occupancy Permit
Citizens Charter document: occupancy-permit.jpg

Related Services

No related services available.