Alaen sakey ya occupancy permit manlapud say Mapandan MEO. RA 11032 panagproseso times: 3–20 working saray agew.

Deskripsyon

Say occupancy permit et mangipanengneng ya natapos tan na-inspect so gusali odino structure unong ed inaprubaan a plano tan National Building Code. Kailangan iya sakbay ya legal ya okupaan odino usaren so antokaman a gusali.

Saray Kinakailangan

  • Xerox copy na inaprubaan building permit
  • Apoy safety inspection sertipiko (manlapud BFP)

Proseso

  1. Man-request sakey ya final inspection manlapud say Munisipal Engineering Opisina.
  2. Ipasa say bilang-built plans tan inspection ireport.
  3. Obtain sakey ya apoy safety inspection sertipiko manlapud say BFP.
  4. Ipasa amin saray dokumento pian say MEO parad usisaen.
  5. Awat say occupancy permit upon aprubasyon.

Detalye na Serbisyo

Opisina ya Mangasiwa: Munisipal Engineering Opisina (MEO)

Klasipikasyon: Simple

Paraan: in-person

Oras na Panangproseso: 3 agew na trabaho (Simple) / 7 agew na trabaho (Complex) / 20 agew na trabaho (Highly Technical) per RA 11032

Bayarin: Bilang scheduled nen say MEO

Iner a Pag-aplayan: Munisipal Engineering Opisina, Main Munisipal Building, Poblacion

Kontak: (075) 636-9382 / 0918-962-7423

Pinanlapuan: Mapandan Citizen’s Charter

Kaukolan a Na-update: August 2025

I-ulat so aliwan a tama ya impormasyon

Na-scan a Dokumento

Na-scan a pahina manipud ed opisyal a Mapandan Citizen’s Charter ya mangipabitar ed saray kinakailangan, bayarin, oras na panagproseso, tan responsable a staff para ed serbisyo.

Citizens Charter parad Occupancy Permit
Dokumento na Citizens Charter: occupancy-permit.jpg

Kaiba a Serbisyo

Anggapo’y available a kaiba a serbisyo.