Electrical Permit

Get an electrical permit from the Mapandan Municipal Engineer. Required for all electrical installations and wiring.

Description

An electrical permit is required for electrical installations and wiring within Mapandan. The Municipal Engineer evaluates the application, conducts site inspection, computes fees based on total connected loads, and endorses to the Zoning Officer and BFP for compliance. The permit is issued after all clearances are obtained.

Requirements

  • Confirmation of adjoining lot owners
  • Barangay Clearance
  • Certified true copy of Tax Declaration
  • Xerox copy of land title (if any)
  • Latest tax payment
  • Community Tax Certificate
  • Signed & sealed form of electrical permits
  • Application for zoning clearance
  • Affidavits

Procedure

  1. Report to Engineering Office for assessment. Staff provides necessary forms (15 min).
  2. Fill up electrical permit forms and submit to the Building Official.
  3. Staff evaluates requirements and conducts site inspection (30 min + 1 hour).
  4. Staff computes assessment fee and endorses to Zoning Officer & BFP (15 min + 15 min).
  5. Pay fees at Treasury Office. Zoning officer & Fire Dept conduct inspection (10 min).
  6. Receive Zoning/Locational & Fire Safety clearance (15 min).
  7. Receive the Electrical Permit (2 min).

Service Details

Responsible Office: Municipal Engineer's Office

Classification: Simple

Mode: in-person

Processing Time: ~2 hours

Fee: Varies based on total connected loads

Where to Apply: Municipal Engineer's Office, Main Municipal Building, Poblacion

Contact: (075) 696-0831

Source: Mapandan Citizen's Charter

Last Updated: August 2025

Report incorrect information

Scanned Document

Scanned page from the official Mapandan Citizen's Charter listing the requirements, fees, processing time, and responsible staff for the service.

Citizens Charter for Electrical Permit
Citizens Charter document: electrical-permit.jpg